Current Status

Sr. No.         Name

Capacity

MW

 Location   Tariff Regime      EPA / IA    Current Status Remarks
WIND
Projects in Operation (Acheived COD)
1 M/s FFC Energy Limited 49.50 Jhimpir Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on  16th May, 2013
2 M/s Zorlu Enerji Pakistan (Pvt.) Limited 56.40 Jhimpir Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on  26th July, 2013
3 M/s Three Gorges Pakistan First Wind Farm (Pvt.) Limited 49.5 Jhimpir Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on 25th  November, 2014
4 M/s Foundation Wind Energy II (Pvt.) Limited 50 Gharo Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on 10th December, 2014
5 M/s Foundation Wind Energy –I Limited 50 Gharo Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on 11th April, 2015
6 M/s Sapphire Wind Power Company Limited 52.80 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Operational Achieved COD on 21st November, 2015
Total Commissioned Project capacity 308.2
Project Under Construction (Achieved Financial Close)
7 M/s Yunus Energy Limited 50 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD  Expected  in August, 2016
8 M/s Sachal Energy Development Pvt. Limited 49.50 Jhimpir Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD  Expected in June, 2017
9 M/s Metro Power Company Limited 50 Jhimpir Cost Plus Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected in August, 2016
10 Tapal Wind Energy Pvt. Limited 30 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected in June, 2016
11 M/s United  Energy Pakistan Pvt. Limited 99 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected in September, 2016
12 M/s Hydro China Dawood Power Pvt. Limited 49.50 Gharo Upfornt Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected  in September, 2016
13 M/s Master Wind Energy Limited 49.50 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected in September, 2016
14 M/s Tenega Generasi Limited 49.50 Gharo Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected  in September, 2016
15 M/s Gul Ahmed Wind Power Ltd 50 Jhimpir Upfront Signed EPA with CPPA/NTDCL and IA with GOP (AEDB) Under Construction - Achieved FC COD Expected  in September, 2016
Total Underconstruction Project capacity 477
Projects in Pipeline
16 M/s Jhampir Wind Power Limited 50 Jhimpir Upfront Signed EPA With CPPA/NTDCL , IA Negotiation yet to be started Upfront tariff  Awarded-LOS Issued –Expected FC  in  August, 2016 Expected COD in 1st QTR of 2018
17 M/s Hawa Energy Pvt. Limited 50 Jhimpir Upfront Singed EPA with CPPA/NTDCL, IA negotiation yet to be started 

Upfront tariff  Awarded-LOS Issued –Expected FC  in  August, 2016 Expected COD in 1st QTR of 2018
18 M/s Hartford Alternative Energy Pvt. Limited 50 Jhimpir Upfront Stage not reached yet Feasibility study approved by AEDB; Upfront Tariff Awarded. Expected FC in March, 2017 Expected COD in  2nd QTR 2018
19 M/s Three Gorges Second Wind Farm Pakistan Limited 49.5 Jhimpir Upfront Stage not reached yet Feasibility study approved by AEDB; Upfront Tariff Awarded. Expected FC in March, 2017 Expected COD in  2nd QTR 2018
20 M/s Three Gorges Third Wind Farm Pakistan (Pvt.) Limited 49.5 Jhimpir Upfront Stage not reached yet Feasibility study approved by AEDB; Upfront Tariff Awarded. Expected FC in March, 2017 Expected COD in  2nd QTR 2018
21 M/s Tricon Boston Consulting  Corporation Pvt. Limited (A) 50 Jhimpir Upfront Stage not reached yet Feasibility Study approved by AEDB; Filed Application to NEPRA for award of upfront tariff Expected COD in  2nd QTR 2018
22 M/s Tricon Boston Consulting Corporation Pvt. Limited (B) 50 Jhimpir Upfront Stage not reached yet Feasibility Study approved by AEDB; Filed Application to NEPRA for award of upfront tariff Expected COD in 2nd QTR 2018
23 M/s Tricon Boston Consulting Corporation Pvt. Limited (C) 50 Jhimpir Upfront Stage not reached yet Feasibility Study approved by AEDB; Filed Application to NEPRA for award of upfront tariff Expected COD in  2nd QTR 2018
24 M/s Zephyr Power Pvt. Limited 50 Gharo Upfront Stage not reached yet Feasibility  study approved by AEDB; Filed Application  to NEPRA for award of Upfront Tariff Expected COD in  4th QTR 2018
25 M/s Western Energy Pvt. Ltd 50 Jhimpir Upfront Stage not reached yet Feasibility Study approval is  in Process Expected COD in  1st  QTR 2019
26 M/s China Sunec Energy Pvt. Limited 50 Nooriabad Upfront EPA & IA Negotiation yet to be started In process of filing  the tariff application to NEPRA Expected COD in 1st  QTR 2019
27 M/s Burj Wind Energy Pvt. Limitd 14 Gajju Cost Plus Stage not reached yet Feasibility Study verification in Process Expected COD in  1st  QTR 2019
28 Trans Atlantic Energy (Pvt.) Limited 50 Jhimpir     In Process of Development of Feasibility Study
29 M/s Shaheen Foundation PAF 50 Jhimpir In Process of Development of Feasibility Study
Total Projects in Pipeline Capacity 663