PROCESS SCHEDULE FOR ISSUANCE OF NET METERING CERTIFICATE TO DOMESTIC/FOREIGN INVESTORS UNDER AEDB CERTIFICATION REGULATIONS

PROCESS SCHEDULE FOR ISSUANCE OF NET METERING CERTIFICATE TO DOMESTIC/FOREIGN INVESTORS UNDER AEDB CERTIFICATION REGULATIONS (2018)

S.No. Task/Activity Time Line
01 Receipt of company proposal at AEDB
02 Forwarding of proposal to relevant Section of AEDB from CEO Secretariat 01-02 days
03 Forwarding of company’s proposal to Processing Team 03 days
04 Scrutiny of Proposal by Processing Team 07 days
05 Submission of proposals before Evaluation Committee, meeting of Evaluation Committee and issuance of meeting minutes 15-30 days
06 Evaluation Committee recommendations to the relevant section post its meeting 05 days
07 Approval of Evaluation Committee minutes from CEO, AEDB 02-03 days
08 Letters to qualified/ unqualified companies for submission of certification fee and other fees as per Regulations or communication of score card to unqualified firms 03 days
09 Timeframe provided to company to meet the requirements. 07 days
10 Confirmation of BG & Payments by Finance Section 07 days
11 Approval & issuance of certificate 03 days
Total number of days 55-70 days

 

Reference

  1. Submission of proposals before the Evaluation Committee depends upon the number of proposals.
  2. In case if there are shortcomings, these shortcomings are communicated to company for addressing and re-submission of proposal to AEDB within 15 days.
  3. Days mean working days.